Project Management

Regs.jpg

line.jpg

Planning for Project Managing your Building

linesml.jpg

Project Management through Planning is the key to any successful building and will help avoid costly problems and delays. 

If there is one thing the building industry is notable for, it is overpromising on delivery and always, but always being late!

You plan as a matter of course in your business, but how systematic is it? How many times have materials or people not shown up on time - and could the problem have been avoided if you had organised and planned far enough ahead? How much does it cost you while you wait?

The secret to good project management is to be able to think ahead and know:

Because construction requires the integration of numerous trades in your building, the management of subcontractors is an essential part of project management.  As main contractor it is YOU who is totally responsible for all planning and project management.

The system we recommend using is the Project Management Bar Chart. This Bar Chart lists all the activities associated with the project and the time each step takes. Each item is movable, so you can factor delays in on an ongoing basis.

Here’s how to put one together...

line.jpg

Building Your Project Management Spreadsheet

linesml.jpg

Using all this information it's now time to start the actual planning so:

Day to Day management...

While your lines should generally indicate the length of time needed to complete each activity, in some cases there is no essential start and finish time required -- for example, external drainage.  In such cases, the line on your chart should show the earliest possible start time, and most importantly the latest completion time for that activity.  However, on that line it is also essential to show the number of days required to complete the activity so the extent of the work involved is always visible.

Note the latest ordering dates for any prefabricated work such as pre-nailed wall framing, roof trusses, metal windows and doors, timber doors, kitchen joinery, internal fittings and fixtures, to ensure these items are delivered on time.

Also identified on your bar chart should be the BCA Inspections, as these will normally be linked to the completion of activities and play a very significant part in your project management of the building. 

What you have now is an easily understood visual representation of the job. A copy should be on site for all parties to view (showing updates), and is a lever to make everyone involved accountable in achieving your targets. 

Assuming a house with a concrete slab and following the construction sequence as closely as possible, first build a list of steps consisting of the following (you can modify to suit your own needs):

  1. site establishment
  2. site boundaries and building profile
  3. boxing, DPC and reinforcing to perimeter foundations
  4. services under-floor
  5. concrete to perimeter foundations
  6. fill, boxing ,DPC, reinforcing to floor slab and thickenings
  7. concrete to floor slab
  8. erect pre-nailed wall framing
  9. erect pre-nailed roof trusses
  10. external trim
  11. roof cladding
  12. spouting
  13. external wrap including preparing openings
  14. external windows and doors
  15. external cladding
  16. external painting
  17. complete internal wall framing
  18. ceiling battens
  19. plumbing/piping
  20. electrical wiring
  21. door & frames
  22. Internal lining
  23. kitchen installation
  24. fixtures and fittings
  25. plumbing fittings
  26. electrical fittings
  27. external drainage
  28. internal trim
  29. painting
  30. landscaping
  31. cleanup

The range, detail and order of activities will depend on the design and construction of the house, but each sub-contractor should be identified as a separate activity so these can clearly be seen fitting into the programme. More than one step may need to be completed before a specific activity is started, and several activities often can start at the same time. 

Now estimate how many days to allow for each of these activities. Make allowances for things going wrong - you must be reasonably generous in your approach to this number-crunching exercise and not use the ideal number of days.

At first this process may not be that accurate. It is not a guessing game, and the more experience you have the more accurate will be the outcome. Every day on a building site is different. Using a chart like this helps give:

line.jpg

Building Project Management: Your Checklists

linesml.jpg

So, you are about to successfully project manage your next building!

Have you set up your systems and processes and prepared your plan complete with your Project Management Spreadsheet? You can't expect to take up the role without doing your homework, so before starting this role ensure the following are set up:

linesml.jpg
Now you are about to start on site and as this is one of the busiest times, the following is your initial checklist:

linesml.jpg

Running a meeting as a Project Manager

Meetings can be a good communications tool, dealing with problems efficiently and effectively, but they need planning as well. Meetings are often considered a waste of time, but in fact, they can be a very efficient way of communication. Done properly they are an excellent tool for Project Management.

Follow recognised guidelines and set a proper meeting structure by:

Doing this will open up discussions for frank and honest comments that will resolve and often anticipate problems and will help ensure a smoothly run project.

linesml.jpg

Managing your Project Management Spreadsheet

The bar chart activities, timing and sequencing are useful guide in the planning of your building project and it’s better than going on a best guess estimate.

Its use as a tool to keep on top of subcontractors sequencing of work and being able to spot conflicts and trouble spots well in advance of them happening cannot be undervalued.

Make sure you:

Changes to the proposed dates are a critical time for the project manager. Remember, changes affect numerous parties and you need their support and co-operation. Communication is the key to ensure that what you've changed is known by everybody and you are totally responsible for that communication.

One thing is for sure, like the first price the client hears, the first completion date the client hears for his building is the one they will always remember, irrespective of all the changes that occur and the discussions and agreements made later.

Be realistic and if necessary overgenerous when giving approximate building completion dates to clients. Use only achievable target dates when establishing times for activities and setting the overall programme timeframe for the project,  you end up gaining a reputation for completing buildings on time.

linesml.jpg

Using your bar chart for Resource Allocation

The calendar contract period that runs across the top your bar chart allows for resources used over a period of time to be visually identified and tracked. Resources for your building operations generally relate to plant and equipment.  Some of these are for specific site activities, while others are for preliminary and general items for general site operations. For example:


These can all be listed at the bottom of the chart in the first column and the calendar date for use on-site boxes filled in to show when they are needed on site.

linesml.jpg

Using your bar chart for Labour Allocation

Allocation of labour can similarly be identified on your bar chart to align with the activities, and the number of staff working on site can be visually identified. For the builder such labour allocation is best broken down into general and specialist trade skills and supervision for such roles as:

Such items are also listed down the left-hand column of the bar chart and the appropriate days across the chart relevant to each activity filled in.

Such information will allow you to juggle staff with particular expertise between sites, balance the number of staff on site over certain periods and be useful for quick visual identification of who is on site at any particular time.

However, a separate colour used for sub-contractor specific activities identified in the main part of your bar chart will show the number of different subcontractors that are on site at a particular time.

Note: Use the chart to determine the allocation of supervisory or management staff on site, once the full extent of the site operations and personnel and resources used becomes obvious.

linesml.jpg

Writing a report as a project manager

Properly presented, reports are vital to the construction process because of the everyday uniqueness of building operation and the need for proper documentation. Keep photographic documentation and write notes after every incident. Don't forget your responsibilities for Health and Safety on site, Code of Compliance Certification and adequate construction insurance is in place.

Make sure it is:

The basic format of a building project report is:

  1. Name of Project.
  2. Summary (how close to deadline did it finish, how close to budget, major issues, successes briefly covered off).
  3. Construction breakdown into broad sections with notes on each section in detail.
  4. Items from summary but in more detail.
  5. Site issues, personnel.
  6. How subcontractors performed.
  7. Materials’ performance.
  8. Suppliers’ delivery timing.
  9. Issues with BCAs, etc.
  10. Conclusion with discussion and recommendations.